Daunia Coal Mine in the Bowen Basin near Moranbah is the ninth coal mine built by BMA. Golding successfully delivered two infrastructure projects to prepare the mine for operation: a contract for bridges and crossings; and a contract for civil works.
The scope for the bridges and crossings contract involved:
- 70m-wide and 46m-long (three spans of 13m, 20m and 13m) rail overpass bridge
- Three 15m bridges
- Conveyor reclaim tunnel and load-out facilities bulk earthworks
- Temporary public access road around rail bridge and a permanent access road under the rail bridge
- Concrete works and associated civil works at the reclaim tunnel exit to the conveyor load-out facilities
- Product conveyor service roads with the Millennium Rail Loop
- Erosion control structures
- New fishway passage culverts and baffle installation
- New light-vehicle access road and upgrade of an existing one.
The scope for the civil works included:
- 1,300,000t of pavement materials
- 3,000,000m3 of earthworks
- 3,200m2 of RE walls
- Eight dams
- 50km of pipes and conduits